Back to field notes
Trade management

Progress Payments: Questions to Resolve Before Paying

Ashley BrennanUpdated 11 July 2026General starting guide

Payment rights and obligations depend on the jurisdiction, parties, work, value calculation, contract, claim, evidence, notices, and current law. This article does not recommend a deposit, milestone percentage, retention, or payment schedule.

What is a progress claim?

A progress claim is a request for payment under a contract or applicable payment regime. It may refer to work performed, materials, a milestone, time, or another agreed basis. The label alone does not establish that the claim is valid, due, correctly valued, or supported.

Before paying, reconcile the claimant, contract, approved variations, scope, tax invoice, period, amount, evidence, previous payments, credits, retention or security, and bank details. Obtain legal, accounting, lender, and technical advice where appropriate.

Do not copy a generic percentage table

A percentage that appears sensible in an example can still conflict with current law, front-load payment, fail to match actual progress, omit evidence, or allocate material and insolvency risk badly. Equally, a percentage alone does not prove misconduct or financial instability.

Ask an appropriately qualified adviser to review the proposed payment structure for the actual contract and jurisdiction before commitment. Australian Consumer Law and any other non-excludable rights continue to apply.

Questions for the proposed schedule

1.

Which contract, legislation, and payment regime applies to the parties and work?

2.

What deposit or advance payment is proposed, what does it fund, and what current limit or rule applies?

3.

What exact work, material, delivery, test, certificate, or other objective evidence triggers each claim?

4.

Who assesses the claim, by when, and what notice or response process applies?

5.

When is an amount due, how is tax treated, and which entity and account should be paid?

6.

How are variations, omissions, defects, incomplete work, delay, set-off, suspension, termination, and disputes handled?

7.

Does title to materials pass, where are they stored, who insures them, and what happens if the contract ends?

8.

Is retention, security, a trust arrangement, or another mechanism proposed, and is it lawful and suitable?

Evidence and assessment

Define the evidence needed for each claim before the claim arrives. Depending on the contract and work, relevant records might include measured quantities, delivery records, photographs, test results, certificates, inspection records, approved variations, statutory declarations, warranties, or professional certification. This list is not complete and does not establish what you are legally entitled to demand.

Separate administrative completion from technical, statutory, or contractual acceptance. A paid invoice, completed checklist, site photograph, or app status does not by itself certify compliant or defect-free work.

Retention and other security

Retention is a contractual security mechanism. Whether it is lawful, suitable, and how it must be held, claimed, released, accounted for, or disputed depends on current law and the contract. Do not withhold, set off, or use another party's money without advice.

Other mechanisms may carry different cost, insolvency, trust, documentation, and administration risks. Obtain project-specific legal and financial advice rather than selecting a mechanism from a template.

Cash-flow planning

Map the proposed claims, finance drawdowns, taxes, authority payments, long-lead deposits, contingencies, and known commitments over time. Use scenarios and update them when evidence changes. A planning calendar does not alter contractual due dates or lender requirements.

Bildr can record the payment amounts, dates, milestones, and notes you supply. It does not approve a claim, certify completed work, interpret the contract, or determine whether payment is legally due.

Put the agreed process in writing

Record the contract value, deposit, claim basis, evidence, assessment, notices, due dates, tax treatment, variations, defects, completion, security, release, dispute, and bank-detail verification process in the appropriate contract documents. Obtain advice on required forms and terms.

The Trade Scope Planning Worksheet provides blank planning fields only. It is not a contract or legal advice.
This article sits within the Owner-Builder Planning Guide, a broader view of the journey from early planning through to handover.
About this article: It may combine general research prompts, personal commentary, simplified examples and fictional scenarios. Do not treat any figure, timeline, quote, event, project status or outcome as a prediction for your build. Content may be incomplete or out of date and is not financial, legal, insurance, tax, engineering, quantity-surveying, compliance or construction advice. Check current project-specific information with official sources and appropriately qualified professionals.
Bring it back to your build

Put the plans, numbers and next decisions in one maintained record.

Bildr helps you organise a residential owner-build before work starts, then keep budgets, quotes, dates and follow-up current as the job moves.

Use your own plans. Review Bildr’s first reading and answer five tailored questions free. No card.